IDXChannel – Acting Director General of Railways og The Ministry of Transportation Risal Wasal stated that progress in construction of Jakarta-Bandung fast train had reached 91.70 percent.
Wasal said the project will have four station, Halim Station, Karawang Station, Padalarang Station and Tegalluar Station, as well as one depot in Tegalluar.
Wasal noted that the Directorate General of Railways as a regulator also helped prepare operation through human resource certification testing feasibility of facilities and infrastructure and security assessments.
KAI is preparing two train services that will support the Jakarta-Bandung fast train connectivity the Jabodetabek LRT and Feeder Train.
"Watch our show IDX Channel Official Youtube on the Market Headlines Program, Friday (9/12/2022) with the theme Construction Progress of Jakarta Bandung Fast Train Reaches 91,7 Percent.