President Jokowi conducted a review at three points, namely the Ciliwung River inlet on Jalan Otista, the arriving shaft on Jalan Otista III, and the outlet point on the East Flood Canal (KBT). The total length of the Ciliwung River sodetan tunnel to KBT reaches 1.2 kilometers and when reviewed, work is being carried out from the inlet to the arriving shaft along 590 meters.
"The work from the inlet to the arriving shaft is 590 meters and this is among the longest in the world," continued Farida.
Sodetan Kali Ciliwung has two tunnels with a diameter of 3.5 meters each. The presence of the sodetan will reduce water discharge by up to 33 cubic meters per second at the time of the standby flood status of four and 63 cubic meters per second at the time of the standby flood status of one.
"Watch our show IDX Channel Official Youtube on the Market Headlines Program, Tuesday (24/1/2023) with the theme The Ciliwung Bypass Expected to Overcome Flooding in Jakarta.
(DKH)